Build progress billing from the contract.
A schedule of values divides the contract into billable parts of the work. Each reporting period updates progress against those line items, including eligible stored materials where the contract permits them. Approved change orders should have a clear trail into the revised contract and the billing schedule.
Use consistent cutoff dates. Keep the current application, supporting documentation, prior applications and revisions together so the current request can be reconciled without rebuilding the job history.
A worked progress-billing example
Assume a $1,000,000 contract, a single illustrative 10% retainage rate and no separate stored-material calculation. Completed work to date is $600,000. The previous certified amount was $360,000 after retainage.
| Line | Calculation | Amount |
|---|---|---|
| Completed work to date | Cumulative eligible work | $600,000 |
| Retainage held to date | $600,000 × 10% | $60,000 |
| Amount earned less retainage | $600,000 − $60,000 | $540,000 |
| Previous certificates | Cumulative previously certified amount | $360,000 |
| Current payment requested | $540,000 − $360,000 | $180,000 |
Previous certification is not the same as cash received.
If a previously certified invoice is still unpaid, it stays in the collection picture. It should not be added to the current application again merely because the money has not arrived.
In this example, $60,000 remains held as retainage. The 10% rate is an assumption, not a universal rule; the contract and applicable requirements determine rates and release conditions.
Manage retainage as its own cash-flow question.
Track the held balance by job, customer and application. Keep the release milestone and required documents visible. Separate retainage that is still conditional from amounts that have been approved for release and are awaiting payment.
On the purchasing side, review subcontractor retainage separately from customer retainage. The amounts, timing and contractual conditions do not necessarily match. A project can show a margin while cash is still tied up in both ordinary receivables and holdbacks.
Connect billing to the wider job picture.
Structally’s approach keeps the contract, approved changes, costs and billing context connected. A clear billing view should explain the revised contract value, the amount submitted, the amount held and the amount collected.
Billing progress does not automatically determine recognized accounting revenue. Use the WIP reporting example to see why those measures can differ.
- Reconcile the schedule of values to the revised contract.
- Check prior applications and retained amounts before each new request.
- Identify missing approvals and closeout documents early.
- Track collections separately from billed and earned amounts.