01 / Connect the job and the books.

Construction accounting combines company financial records with the economics of individual projects. The company needs an accurate ledger, receivables, payables and cash records. The project team needs to understand the budget, the work completed and the cost of finishing. Those views should be connected by the underlying transactions.

Consider a $12,000 supplier invoice for concrete. The ledger explains how the amount is accounted for. The job record explains which project used it, which phase it belongs to and whether it was expected. A purchase order can explain the original commitment. The invoice and receiving record provide the evidence behind the amount.

A consistent job, cost-code and category structure makes those connections practical. Avoid using a different set of categories for estimating, purchasing and cost reporting unless there is a clear mapping between them.

02 / Build the cost picture.

Four cost measures answer four different questions. A budget is the plan. Actual cost is what has been recorded. An open commitment is spending contracted for but not yet reflected in actual costs. Estimated cost to complete is the current forecast for all remaining work, including open commitments and uncommitted work.

Four questions to bring to the project review
QuestionLook atCheck before relying on it
What did we plan to spend?Original and revised budgetsWhich changes were approved?
What has been incurred?Actual job costsAre cutoff and coding complete?
What have we already committed?Open POs and subcontractsHave invoiced costs reduced the open balance?
What remains to finish?Estimate to completeDoes it include all remaining work?

Labor deserves the same discipline. Reconcile finalized wages and employer burden to the jobs and cost codes receiving those allocations. Keep the basis for burden allocations documented. Do not confuse a useful labor-cost report with payroll calculation or compliance reporting.

See a full job-cost and commitments example

03 / Update the forecast before reading the margin.

Suppose a job has a revised cost budget of $1,250,000. Actual costs are $720,000 and open commitments are $310,000. That leaves $220,000 of uncommitted budget. It does not tell you whether $220,000 is enough for all the remaining work.

If the team expects another $260,000 beyond the open commitments, forecast final cost is $1,290,000. The job is forecast to exceed its cost budget by $40,000. At a contract value of $1,500,000, projected job gross profit is $210,000, before costs outside the job estimate.

A forecast needs a date and an explanation.

Record who supplied the assumptions, when they were updated and what changed. A total with no explanation is difficult to challenge or improve.

A WIP schedule extends this review into accounting. It compares project forecasts, progress, revenue and billing positions. Revenue recognition depends on the applicable framework and contract facts; billing or cash collection alone does not settle the answer.

Follow a worked WIP example

04 / Separate billing, retainage and cash.

A payment application may show substantial progress while part of the amount remains held as retainage. An approved application can also remain unpaid. Keep submitted, certified, held and collected amounts identifiable so a payment delay does not disappear inside a single total.

For example, $600,000 of cumulative eligible work with an illustrative 10% holdback leaves $540,000 after retainage. If previous certificates total $360,000, the current request is $180,000. The $60,000 retained is a separate collection and release question. Actual contract terms determine the applicable calculation.

Build a short-term cash view from expected collections and upcoming payroll, vendor and subcontractor obligations. Review the timing of retainage release, approval bottlenecks and other items that can move a receipt into a later period. A job’s projected gross profit is not its available cash.

Walk through the billing and retainage example

05 / Close with a useful checklist.

  1. Confirm the cutoff. Review invoices, accruals and payroll allocations belonging to the period.
  2. Reconcile job costs. Resolve differences between project detail and the relevant ledger accounts.
  3. Update commitments. Reduce open balances for recorded costs and review cancellations and approved changes.
  4. Refresh the forecast. Ask project managers about quantities, productivity, outstanding scope and cost to complete.
  5. Review WIP together. Explain margin changes and earned-versus-billed differences before posting adjustments.
  6. Check billing and retainage. Identify missing applications, approvals, closeout documents and collection follow-up.
  7. Keep the supporting record. Preserve the source documents, review date and explanation behind material changes.

The purpose of the close is a financial picture that can be explained and used. A recurring review with accounting and project teams is often more useful than adding another report with the same unresolved inputs.

About this guide and its sources

Written for Structally using original explanations and illustrative figures. It introduces operating concepts; it is not a substitute for advice on your contracts, accounting policies or tax position.

Source pages checked October 2, 2026.